Paper | Title | Page |
---|---|---|
MOPEB011 | Magnetic Field Ripple Reduction of Main Magnets of the J-PARC Main Ring using Trim Coils | 301 |
|
||
Efforts have been made to reduce the magnetic field ripple of the bending, quadrupole and sextupole magnets of the J-PARC main ring using the trim coils of the magnets. The quadrupole magnet has 24 turn main coil and 11 turn trim coil per pole those can be considered as a primary winding and a secondary winding of a transformer. When the trim coil is shorted, the induced trim coil current cancels the field ripple. The field ripple of the quadrupole magnet was reduced by a factor of 6 by shorting trim coil. The trim coil current, however, deforms the acceleration field pattern if the coil is shorted all the time of the current pattern of flat bottom, acceleration, flat top and recovery. The MOSFET relay was used to short the coil and to reduce the field ripple during the flat bottom and flat top. The circuits were built for the quadrupole and sextupole magnets. The plan has been made to wind optimized trim coils for the bending magnets. |
||
MOPE012 | Performance of the Main Ring BPM during the Beam Commissioning at J-PARC | 981 |
|
||
Experiences of operating BPM's during beam commissioning at the J-PARC MR are reported. The subjects are: (1) bug report, statistics and especially the effect of a beam duct step, (2) position resolution estimation (<30 micrometers with 1 sec averaging), (3) beam based alignment. |
||
WEPD062 | Magnetic Field Measurement and Ripple Reduction of Quadrupole Magnets of the J-PARC Main Ring | 3239 |
|
||
The power supply current ripple of the quadrupole magnets of the J-PARC main ring has been measured to be the order of 10-4. The magnetic field of the quadrupole magnets has been measured and the ripple frequency distribution of each magnet was observed to be depending on where the magnet is in the magnet chain. A transmission line model for the cable and magnets was able to explain the distribution. The field ripple made by the common mode current ripple was reduced by changing the magnet cabling to be symmetrical with respect to the N and S poles of the quadrupole magnets. The common mode ripple was drastically reduced. The normal mode ripple of 600, 1200 and 1800 Hz however remained. The field ripple was further reduced using resistors those are connected in parallel to the magnet coils and bypass the current ripple. It was effective to the higher frequency ripple of 1200 and 1800 Hz and the effect was in a good agreement with an electric circuit simulation program LTspice. |
||
THPEB015 | Beam Injection Tuning of the J-PARC Main Ring | 3915 |
|
||
The beam commissioning of J-PARC (Japan Proton Accelerator Research Complex) MR (Main Ring) was started from May 2008 and is in progress. As usual, injection tuning is in the first stage and strongly related to other tuning items. Starting with design schemes, making adjustment due to leakage field influence from injection septum, doing envelope matching considering dilution of beam profile in Main Ring are reported in this paper. The 'Without bump' scheme was got on June 15th 2008, while 'With bump' scheme on February 15th 2009. Beam orbit betatron oscillation to the MR close orbit which cause by injection error is less than 1 mm both in horizontal and vertical direction. Meanwhile, Beam Optics matching for 3 GeV beam from 350BT to MR has been well done too, which is also very important. * T. Koseki, Challenges and Solutions for J-PARC Commissioning and Early Operation, in these proceedings |
||
THPEB016 | Beam Fast Extraction Tuning of the J-PARC Main Ring | 3918 |
|
||
The beam commissioning of J-PARC/MR has been started from May 2008 and is in progress*. One key purpose of MR commissioning is the 30 GeV beam fast extraction to Neutrino beam line, which reflect the overall commissioning result. In the MR, the third straight section is assigned for the fast extraction. 5 kickers and 8 septa were installed there, which can give beam a bipolar kick to inside or outside of MR. Inside kick means beam to Neutrino Oscillation Experiment, while outside kick means beam dumped to abort line. However before commissioning, the measured magnetic field distribution of each septa shows non-linear profile along the horizontal direction. In order to find the influence, a simulation with these measured field has been performed. Depends on this study and some OPI (Operation Interface) made by code SAD for orbit modification online, fast extraction of 30 GeV beam to Neutrino line has been achieved on April 23rd 2009. Beam orbit have been tuned to less than 0.5 mm and 0.1 mrad in both horizontal and vertical at the beginning of Neutrino line, which is also the end of MR fast extraction. And so far, 100 kW continual operation to neutrino line have been achieved, too. * T. Koseki, "Challenges and Solutions for J-PARC Commissioning and Early Operation", in these proceedings |
||
THPE069 | Simulation of Space Charge Effects in JPARC | 4677 |
|
||
Nonlinear space charge interaction in high intensity proton rings causes beam loss, which limits the performance. Simulations based on particle in cell method has been performed for JPARC-Rapid Cycle Synchrotron and Main Ring. Beam loss estimation during acceleration and resonances analysis are discussed with various simulations using dynamic and frozen models. |