A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Chen, L.J.

Paper Title Page
THPEA075 Installation and Commissioning of the 200m Flexible Cryogenic Transfer System 3843
 
  • M.-C. Lin, L.-H. Chang, M.H. Chang, L.J. Chen, W.-S. Chiou, F.-T. Chung, F. Z. Hsiao, Y.-H. Lin, C.H. Lo, H.H. Tsai, M.H. Tsai, Ch. Wang, T.-T. Yang, M.-S. Yeh, T.-C. Yu
    NSRRC, Hsinchu
  • M. Di Palma, S. Lange, H. Lehmann, K. Schippl
    NEXANS Deutschland Industries AG & Co. KG, Moenchengladbach
 
 

The National Synchrotron Radiation Research Center is constructing the Taiwan Photon Source (TPS), a 3-GeV synchroton facility. The superconducting radio frequency (SRF) cavity modules are selected as the accelerating cavities in the electron storage ring. A test area for the SRF modules is established in the RF laboratory, which includes cryogenic environment, RF transmitter, low level RF control system, and radiation shielded space. The liquid helium is transferred from the cryogenic plant in the experimental area of the Taiwan Light Source (TLS), which is not only far from the RF laboratory but also characterized by a complicated route of 205 meters. The main concerns on the cryogenic transfer are the installation difficulty, heat loss, two-phase flow, and pressure loss. Instead of a multi-channel transfer line, which would request a long installation period on radiation-restrict area, flexible cryogenic transfer lines from Nexans were chosen. The installation period was dramatically reduced to one week. With a test Dewar in the RF lab and valve boxes on both ends of the transfer lines, a long distance cryogenic transfer system was completed and proved to work functional.