A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Arduini, G.

Paper Title Page
MOPEB045 Commissioning of the LHC Magnet Powering System in 2009 376
 
  • M. Solfaroli Camillocci, G. Arduini, B. Bellesia, J. Coupard, K. Dahlerup-Petersen, M. Koratzinos, M. Pojer, R. Schmidt, A.P. Siemko, H. Thiesen, A. Vergara-Fernández, M. Zanetti, M. Zerlauth
    CERN, Geneva
 
 

On 19th September 2008 the Large Hadron Collider (LHC) experienced a serious incident, caused by a bad electrical joint, which stopped beam operation just a few days after its beginning. During the following 14 months the damage was repaired, additional protection systems were installed and the measures to avoid a similar incident were taken (i.e. new layer of the Magnet Quench Protection System [nQPS], more efficient He release valves). As a consequence, a large number of powering tests had to be repeated or carried out for the first time. The re-commissioning of the already existing systems as well as the commissioning of the new ones has been carefully studied, then performed taking into account the history of each of the eight LHC sectors (warm-up, left at floating temperature,'). Moreover, a campaign of measurements of the bus-bar splice resistances has been carried out with the nQPS in order to spot out non conformities, thus assessing the risk of the LHC operation for the initial energy level. This paper discusses how the guidelines for the LHC 2009 re-commissioning were defined, providing a general principle to be used for the future re-commissioning.

 
MOPEC003 Operational Experience during Initial Beam Commissioning of the LHC 456
 
  • K. Fuchsberger, R. Alemany-Fernandez, G. Arduini, R.W. Assmann, R. Bailey, O.S. Brüning, B. Goddard, V. Kain, M. Lamont, A. Macpherson, M. Meddahi, G. Papotti, M. Pojer, L. Ponce, S. Redaelli, M. Solfaroli Camillocci, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

After the incident on the 19th September 2008 and more than one year without beam the commissioning of the LHC started again on November 20, 2009. Progress was rapid and collisions under stable beam conditions were established at 1.2 TeV within 3 weeks. In 2010 after qualification of the new quench protection system the way to 3.5 TeV was open and collisions were delivered at this energy after a month of additional commissioning. This paper describes the experiences and issues encountered during these first periods of commissioning with beam.

 
MOPEC007 Operational Experience during the LHC Injection Tests 468
 
  • K. Fuchsberger, R. Alemany-Fernandez, G. Arduini, R.W. Assmann, R. Bailey, O.S. Brüning, B. Goddard, V. Kain, M. Lamont, A. Macpherson, M. Meddahi, G. Papotti, M. Pojer, L. Ponce, S. Redaelli, M. Solfaroli Camillocci, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

Following the LHC injection tests of 2008, two injection tests took place in October and November 2009 as preparation for the LHC restart on November 20, 2009. During these injection tests beam was injected through the TI2 transfer line into sector 23 of ring 1 and through TI8 into the sectors 78, 67 and 56 of ring 2. The beam time was dedicated to injection steering, optics measurements and debugging of all the systems involved. Because many potential problems were sorted out in advance, these tests contributed to the rapid progress after the restart. This paper describes the experiences and issues encountered during these tests as well as related measurement results.

 
TUPD048 Amorphous Carbon Coatings for Mitigation of Electron Cloud in the CERN SPS 2033
 
  • C. Yin Vallgren, G. Arduini, J. Bauche, S. Calatroni, P. Chiggiato, K. Cornelis, P. Costa Pinto, E. Métral, G. Rumolo, E.N. Shaposhnikova, M. Taborelli, G. Vandoni
    CERN, Geneva
 
 

Amorphous carbon coatings with low secondary electron yield have been applied to the liners in the electron cloud monitors and to vacuum chambers of three dipole magnets in the SPS. The electron cloud is completely suppressed for LHC type beams in these monitors even after 3 months air venting and no performance deterioration is observed after more than one year of SPS operation. Upon variation of the magnetic field in the monitors the electron cloud current maintains its intensity down to weak fields of some 40 Gauss, where fast conditioning is observed. This is in agreement with dark traces observed on the RF shields between dipoles. The dynamic pressure rise has been used to monitor the behavior of the magnets. It is found to be about the same for coated and uncoated magnets, apart from a weak improvement in the carbon coated ones under conditions of intense electron cloud. Inspection of the coated magnet is foreseen in order to detect potential differences with respect to the coated monitors. Measurements of the stray fields outside the dipoles show that they are sufficiently strong to induce electron cloud in these regions.

 
TUPD056 Update of the SPS Impedance Model 2057
 
  • B. Salvant
    EPFL, Lausanne
  • G. Arduini, O.E. Berrig, F. Caspers, A. Grudiev, N. Mounet, E. Métral, G. Rumolo, B. Salvant, E.N. Shaposhnikova, C. Zannini
    CERN, Geneva
  • M. Migliorati, B. Spataro
    INFN/LNF, Frascati (Roma)
  • B. Zotter
    Honorary CERN Staff Member, Grand-Saconnex
 
 

The beam coupling impedance of the CERN SPS is expected to be one of the limitations to an intensity upgrade of the LHC complex. In order to be able to reduce the SPS impedance, its main contributors need to be identified. An impedance model for the SPS has been gathered from theoretical calculations, electromagnetic simulations and bench measurements of single SPS elements. The current model accounts for the longitudinal and transverse impedance of the kickers, the horizontal and vertical electrostatic beam position monitors, the RF cavities and the 6.7 km beam pipe. In order to assess the validity of this model, macroparticle simulations of a bunch interacting with this updated SPS impedance model are compared to measurements performed with the SPS beam.

 
THPEB006 Optics Measurements and Transfer Line Matching for the SPS Injection of the CERN Multi-turn Extraction Beam 3888
 
  • E. Benedetto
    National Technical University of Athens, Zografou
  • G. Arduini, S. Cettour Cave, F. Follin, S.S. Gilardoni, M. Giovannozzi, F. Roncarolo
    CERN, Geneva
 
 

Dispersion and beam optics measurements were carried out in the transfer line between the CERN PS and SPS for the new Multi-Turn Extraction beam. Since the extraction conditions of the four islands and the core are different and strongly dependent on the non-linear effects used to split the beam in the transverse plane, a special care was taken during the measurement campaigns. Furthermore, an appropriate strategy was devised to minimize the overall optical mismatch at SPS injection. All this led to a new optical configuration that will be presented in detail in the paper.