THPEA083 The ALBA Vacuum System: Installation and Commissioning 3861
 
  • E. Al-Dmour, D. Einfeld
    CELLS-ALBA Synchrotron, Cerdanyola del Vallès
 
 

The me­chan­i­cal in­stal­la­tion of the boost­er syn­chrotron of ALBA start­ed in Jan­uary 2009 and fin­ished by hav­ing the sys­tem under vac­u­um in April 2009. The prepa­ra­tion of the boost­er vac­u­um sys­tem for the in­stal­la­tion (par­tial as­sem­bly with the pumps and in­stru­men­ta­tion, bake­out, etc) start­ed al­ready in Septem­ber 2008. For the stor­age ring, the main me­chan­i­cal in­stal­la­tion was done from May to Septem­ber 2009. The av­er­age pres­sure in the boost­er syn­chrotron is in the range of low 10-9 mbar and in the stor­age ring is in the low 10-10 mbar. The prepa­ra­tion of the in­stal­la­tion, the in­stal­la­tion and the pre­sent per­for­mance will be pre­sent­ed in this con­tri­bu­tion. The first round of the boost­er com­mis­sion­ing took place at the end of 2009 and the be­gin­ning of 2010. The first data of the boost­er vac­u­um sys­tem com­mis­sion­ing are pre­sent­ed as well.