The stakeholders of the ESS Integrated Control System (ICS) reside in four parts of the ESS machine: accelerator, target, neutron instruments and conventional facilities. ICS plans to meet the stakeholders’ needs early in the Construction phase, to accelerate and facilitate the Commissioning process by providing and delivering required tools earlier. This introduces the risk that stakeholders will not have had the full set of information required available early enough for the development of the interfacing systems (e.g. missing requirements, undecided design etc.) In order for ICS to accomplish its objectives it is needed to establish a development process that allows a quick adaptation to any change in the requirements with a minimum impact in the execution of the projects. Agile Methodology is well known for its ability to adapt quickly to change, as well as for involving users in the development process and producing working and reliable software from a very early stage in the project. The paper will present the plans, the tools, the organization of the team and the preliminary results of the setup work.
|
|