TUPKF068 JLAB Hurricane Recovery 1102
 
  • A. Hutton, D. Arenius, F.J. Benesch, S. Chattopadhyay, E. Daly, V. Ganni, O. Garza, R. Kazimi, R. Lauze, L. Merminga, W. Merz, R. Nelson, W. Oren, M. Poelker, T. Powers, J.P. Preble, C. Reece, R.A. Rimmer, M. Spata, S. Suhring
    Jefferson Lab, Newport News, Virginia
 
  Hurricane Isabel, originally a Category 5 storm, arrived at Jefferson Lab on September 18 with winds of only 75 mph creating little direct damage to the infrastructure. However, electric power was lost for four days allowing the superconducting cryomodules to warm up and causing a total loss of the liquid helium. The subsequent recovery of the cryomodules and the impact of the considerable amount of opportunistic preventive maintenance provides important lessons for all accelerators complexes, not only those with superconducting elements. The details of how the recovery process was structured and the resulting improvement in accelerator availability will be discussed in detail.