A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z    

Stivanello, F.

Paper Title Page
TUPKF024 Operation Experience with ALPI Nb/Cu Resonators 1018
 
  • A.M. Porcellato, L. Bertazzo, M. De Lazzari, D. Giora, V. Palmieri, S. Stark, F. Stivanello
    INFN/LNL, Legnaro, Padova
 
  The refurbishing, by replacing the Pb superconducting film by Nb, of ALPI QW accelerating resonators was completed in 2003. All the 52 cavities are now in operation showing a large increase in the average accelerating field, which exceeds 4.5 MV/m (21 MV/m pick electrical surface field). The performance of renewed resonators has been increasing with time reaching 6MV/m in the last produced units. The increase in ALPI performance and the advantage in conditioning and setting time obtained by the upgrading process will be reported.