Park, S.

Paper Title Page
TUPKF061 The SPEAR3 RF System 1084
 
  • P.A. McIntosh, S. Allison, P. Bellomo, S. Hill, V. Pacak, S. Park, J.J. Sebek, D.W. Sprehn
    SLAC, Menlo Park, California
 
  SPEAR2 was upgraded in 2003, to a new 3rd Generation Light Source (3GLS) enabling users to take better advantage of almost 100x higher brightness and flux density over its predecessor SPEAR2. As part of the upgrade, the SPEAR2 RF system has been re-vamped from its original configuration of one 200 kW klystron feeding a single 358.5 MHz, 5-cell aluminum cavity; to a 1.2 MW klystron feeding four 476.3 MHz, HOM damped copper cavities. The system installation was completed in late November 2003 and the required accelerating voltage of 3.2 MV (800 kV/cavity) was very rapidly achieved soon after. This paper details the SPEAR3 RF system configuration and its new operating requirements, highlighting its installation and subsequent successful operation.  
THPKF082 The Completion of SPEAR 3 2448
 
  • R.O. Hettel, R. Akre, S. Allison, P. Bellomo, R.F. Boyce, L. Cadapan, R. Cassel, B. Choi, W.J. Corbett, D. Dell'Orco, T. Elioff, I. Evans, R. Fuller, S. Hill, D. Keeley, N. Kurita, J. Langton, G. Leyh, C. Limborg-Deprey, D. Macnair, D.J. Martin, P.A. McIntosh, E. Medvedko, C.-K. Ng, I. Nzeadibe, J. Olsen, M. Ortega, G.C. Pappas, S. Park, T. Rabedeau, H. Rarback, A. Ringwall, P. Rodriguez, J.A. Safranek, H.D. Schwarz, B. Scott, J.J. Sebek, S. Smith, T. Straumann, J. Tanabe, A. Terebilo, T.A. Trautwein, C. Wermelskirchen, M. Widmeyer, R. Yotam, K. Zuo
    SLAC/SSRL, Menlo Park, California
 
  On December 15, 2003, 8 1/2 months after the last electrons circulated in the old SPEAR2 storage ring and 5 days after the beginning of commissioning, the first electrons were accumulated in the completely new SPEAR3 ring. The rapid installation and commissioning is a testimony to the SPEAR3 project staff and collaborators who have built an excellent machine and equipped it with powerful and accessible machine modeling and control programs. The final year of component fabrication, system implementation and testing, the 7-month installation period leading up to the beginning of commissioning, and lessons learned are described.