A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z    

Demirkan, M.

  
Paper Title Page
THOACH02 Commissioning of the 500 MeV Injector for MAX-lab 219
 
  • S. Werin, Å. Andersson, M. Bergqvist, M. Brandin, M. Demirkan, M. Eriksson, L.-J. Lindgren, L. Malmgren, H. Tarawneh, E.J. Wallén
    MAX-lab, Lund
  • B. Anderberg
    AMACC, Uppsala
  • G. Georgsson
    Danfysik A/S, Jyllinge
  • G. LeBlanc
    ASP, Melbourne
 
  A 500 MeV new injector system for the storage rings MAX I, II and III have been installed during the winter 2003-4 at MAX-lab. The system consists of two linacs at 125 MeV each, using SLED, and a recirculating system such that the electrons pass the linacs twice, thus reaching a final energy of 500 MeV. The system is injected by a thermionic RF-gun. The commissioning of the complete system will be performed in the spring 2004.  
Video of talk
Transparencies
THPKF056 The MAX IV Facility 2389
 
  • M. Eriksson, Å. Andersson, M. Bergqvist, M. Brandin, M. Demirkan, G. Georgsson, G. LeBlanc, L.-J. Lindgren, L. Malmgren, H. Tarawneh, E.J. Wallén, S. Werin
    MAX-lab, Lund
  • B. Anderberg
    AMACC, Uppsala
  • S. Biedron, S.V. Milton
    ANL, Argonne, Illinois
 
  The MAX IV facility is a planned successor of the existing MAX facility. The planned facilty is described below. It consists of two new synchrotron storage rings operated at different electron energies to cover a broad spectral region and one linac injector. The linac injector is also meant to be operated as a FEL electron source. The two rings have similar low emittance lattices and are placed on top of each other to save space. A third UV light source, MAX III, is planned to be transfered to the new facility.