THPKF082 The Completion of SPEAR 3 2448
 
  • R.O. Hettel, R. Akre, S. Allison, P. Bellomo, R.F. Boyce, L. Cadapan, R. Cassel, B. Choi, W.J. Corbett, D. Dell'Orco, T. Elioff, I. Evans, R. Fuller, S. Hill, D. Keeley, N. Kurita, J. Langton, G. Leyh, C. Limborg-Deprey, D. Macnair, D.J. Martin, P.A. McIntosh, E. Medvedko, C.-K. Ng, I. Nzeadibe, J. Olsen, M. Ortega, G.C. Pappas, S. Park, T. Rabedeau, H. Rarback, A. Ringwall, P. Rodriguez, J.A. Safranek, H.D. Schwarz, B. Scott, J.J. Sebek, S. Smith, T. Straumann, J. Tanabe, A. Terebilo, T.A. Trautwein, C. Wermelskirchen, M. Widmeyer, R. Yotam, K. Zuo
    SLAC/SSRL, Menlo Park, California
 
  On December 15, 2003, 8 1/2 months after the last electrons circulated in the old SPEAR2 storage ring and 5 days after the beginning of commissioning, the first electrons were accumulated in the completely new SPEAR3 ring. The rapid installation and commissioning is a testimony to the SPEAR3 project staff and collaborators who have built an excellent machine and equipped it with powerful and accessible machine modeling and control programs. The final year of component fabrication, system implementation and testing, the 7-month installation period leading up to the beginning of commissioning, and lessons learned are described.